The 1-Acre vs. 5-Acre SWPPP Rule, Explained
Texas construction sites disturbing 1 to under 5 acres are "small construction activity": they need a SWP3 and a posted Small Construction Site Notice, but no Notice of Intent and no fee. Sites of 5 acres or more are "large construction activity" and must also file an electronic NOI ($225) and a

Published August 13, 2026. Last reviewed August 13, 2026. Technical review: Jim Price, CISEC, CESSWI. Founder, Stormwater Compliant LLC.
Texas construction sites disturbing 1 to under 5 acres are "small construction activity": they need a SWP3 and a posted Small Construction Site Notice, but no Notice of Intent and no fee. Sites of 5 acres or more are "large construction activity" and must also file an electronic NOI ($225) and a Notice of Termination at close-out.
Both tiers need a plan. Only one tier files anything with TCEQ. That distinction is worth getting right in both directions, because paying a fee you do not owe is annoying and skipping one you do owe means building without authorization.

Small vs. Large Construction: The Comparison
| Small construction 1 to under 5 acres | Large construction 5 acres and up | |
|---|---|---|
| SWP3 (SWPPP) | Required, in place before construction begins | Required, in place before construction begins |
| Notice of Intent (NOI) | Not required | Required, electronically through STEERS |
| Application fee | None | $225 electronic, $325 paper |
| Site notice form | Small Construction Site Notice, TCEQ-20963 | Large Construction Site Notice, TCEQ-20961 (primary operator) or TCEQ-20962 (secondary operator) |
| Also posted | Signed notice only | Notice plus the first page of the submitted NOI |
| Posting deadline | At least 2 days before construction begins | Before construction begins |
| Copy to MS4 operator | Required | Required |
| Inspections | Same schedule as large sites | Same schedule as small sites |
| Stabilization deadlines | Identical | Identical |
| Notice of Termination (NOT) | Not required | Required, within 30 days of final stabilization |
| Coverage ends | When the site reaches final stabilization | When TCEQ approves the NOT |
If you take one thing from this page, take that table. It is the single most-referenced piece of information in the whole permit.

Small Construction Activity (1 to Under 5 Acres)
You are in this tier if total disturbance is at least one acre but less than five, including everything covered in when a SWPPP is required in Texas: clearing, grading, stockpiles, haul roads, and support activity.
What you owe:
- Develop and implement a site-specific SWP3 before construction begins. Not a template with your address typed in. A plan matching your actual drainage, topography, and construction sequence.
- Sign and post the Small Construction Site Notice, TCEQ-20963, at least two days before construction begins. It has to be readable by the public and by any inspector from outside the fence, and it stays posted until final stabilization.
- Provide a copy of the notice to the operator of any MS4 receiving your discharge. In San Antonio that generally means the City, and SAWS as co-permittee.
- Inspect, document, and correct on the permit's schedule for the life of the project.
- Reach final stabilization. No termination filing, but the obligation to actually stabilize does not go away.
That is the entire filing burden: one signed notice, posted early, copied to the MS4. No fee, no STEERS account, no submission.
The two-day posting deadline is the part that trips people. It is not "before the first inspection." It is two days before you start work.

Large Construction Activity (5 Acres and Up)
Everything above, plus three things.
File the Notice of Intent electronically through STEERS. The NOI obtains your permit coverage and must be submitted before construction begins. The fee is $225 electronic, $325 on paper. Since September 1, 2018, electronic filing through STEERS has been the default; paper requires an electronic reporting waiver.
Do not leave the STEERS account until the week you need to file. New accounts start in probationary status pending a signed electronic signature agreement, which takes time you may not have. The walkthrough is in filing a Notice of Intent through STEERS.
Post the Large Construction Site Notice, TCEQ-20961, along with the first page of your submitted NOI. Secondary operators post TCEQ-20962 instead.
File a Notice of Termination within 30 days of achieving final stabilization on all portions of the site you are responsible for. This also applies on a transfer of operational control, or if you obtain alternative authorization.
That last item is the one that generates the most avoidable cost in this entire permit. Coverage, and every obligation attached to it, continues until the NOT is submitted and approved by TCEQ. Demobilizing is not terminating. See filing the Notice of Termination.
What Does Not Change at Five Acres
A persistent assumption is that small sites carry lighter ongoing duties. They do not. Once you are regulated, these are identical at both tiers:
- Inspection frequency. At least once every 14 calendar days and within 24 hours of the end of a 0.5-inch-or-greater storm event, or the elective 7-day schedule if documented in your SWP3.
- Stabilization deadlines. Initiate by the end of the next work day where activity has ceased and will not resume within 14 days; complete within 14 days of initiation.
- Corrective action documentation. Fix it and write down that you fixed it, with dates.
- SWP3 amendments. The plan updates as the site changes.
- Recordkeeping. Inspection reports and the plan itself stay available on site.
- Final stabilization at 70% of native background vegetative cover.
The only real difference is the paperwork you file at the beginning and the end. The work in between is the same.
The MS4 Copy Almost Nobody Sends
Both tiers must provide a copy of the site notice, or the NOI, to the operator of any municipal separate storm sewer system receiving the discharge. The SWP3 has to list those MS4 operators by name and address.
This requirement gets skipped constantly, largely because contractors are not sure who the MS4 operator is. In the San Antonio metro it is usually the City of San Antonio, with SAWS acting as co-permittee alongside the City and TxDOT. In unincorporated areas it is typically Bexar County.
It is a two-minute task and it is a documented permit condition. When an inspector asks who you notified and you have no answer, it establishes a tone for the rest of the inspection.
The San Antonio Overlay
One local requirement applies to both tiers and is not in the state permit at all.
Under the City of San Antonio construction stormwater ordinance (2014-06-19-0472, approved June 19, 2014), SAWS enforces TPDES requirements locally as co-permittee with the City and TxDOT. A copy of your NOI or Construction Site Notice must go to stormwaterconstruction@saws.org at least 48 hours before construction-related activities begin.
Forty-eight hours, not two days after you start. It is one of the most commonly missed items in this market and it takes about two minutes.
Sites over the Edwards Aquifer Recharge or Contributing Zone have a much larger consideration: under Part II.C.5 of the permit, construction cannot commence until TCEQ's Edwards Aquifer Protection Program has approved the applicable Water Pollution Abatement Plan or Contributing Zone Plan. That is independent of your acreage tier and independent of your CGP coverage.
Common Mistakes at the Threshold
Calculating acreage from the building footprint. Disturbance includes everything you scrape. Projects that look like 4.2 acres on the site plan land at 5.4 once staging and haul roads are counted, which moves them into the large tier and an NOI they never filed.
Assuming a phased project stays small. If your phases are part of one larger common plan, the plan's total governs. Three 2-acre phases are a 6-acre project.
Filing an NOI you do not owe. On a genuine 2-acre standalone site there is nothing to submit. Some contractors file anyway "to be safe," which costs $225 and creates an authorization they now have to terminate.
Posting the notice on the trailer door. It has to be readable from outside the site by the public and by inspectors. Inside a locked gate does not satisfy it.
Taking the notice down at substantial completion. It stays up until final stabilization.
Skipping the notice because the site is small. The Construction Site Notice is the cheapest item in the permit and among the most frequently cited. See the most common SWPPP violations on San Antonio job sites.
Not Sure Which Tier You're In?
Send us the site plan and we will confirm the disturbed acreage, tell you exactly which filings you owe, and give you a fixed-price scope and timeline for the plan itself. If you are close to the five-acre line, that verification is worth doing before you file anything.
Request a quote or call (210) 776-6515. More about our SWPPP services, and the full permit walkthrough in our field guide to the TCEQ Construction General Permit.
Sources
Common questions
- Do I need an NOI for a 3-acre site?
- No. Small construction activity requires the SWP3 and a posted Small Construction Site Notice, but no NOI and no fee.
- What if my site is exactly 5 acres?
- Five acres and up is large construction activity. At exactly five, you file the NOI.
- Do small sites file a Notice of Termination?
- No. But you still have to achieve final stabilization, and you still have to maintain records showing you did.
- Can I file the NOI on paper?
- Only with an electronic reporting waiver. The default since September 1, 2018 is electronic through STEERS, and paper costs $325 against $225.
- How long does STEERS take?
- The filing itself is quick. Getting the account authorized is not, because new accounts sit in probationary status pending a signed electronic signature agreement. Start it well before you need it.
- Does the acreage tier change my inspection schedule?
- No. Inspection frequency, stabilization deadlines, and recordkeeping are identical at both tiers.
The work behind this article
- Stormwater Pollution Prevention Plan
Site-specific Stormwater Pollution Prevention Plans for Bexar County construction, written to the TCEQ Construction General Permit (TXR150000) and built so your superintendent will actually open the binder.
- 40-Point Stormwater Inspection
One inspector, one tablet, 40 checkpoints. You get the report before our truck leaves the property.
- Post-Construction Stormwater
An annual program that keeps your basins, vaults, and conveyance systems documented, inspected, and in regulatory good standing.
Need help with stormwater compliance on a San Antonio property? We do site walks at no charge.
Request a fixed-price quoteMore field notes from the watershed.
Compliance · 7 minWhen Is a SWPPP Required in Texas?
A SWPPP is required in Texas whenever construction disturbs one acre or more of soil and discharges stormwater to surface water in the state. Projects under one acre are also regulated if they are part of a larger common plan of development or sale. The plan must be in place before construction
Compliance · 14 minTexas SWPPP Requirements: A Field Guide to the TCEQ Construction General Permit
If your project will disturb one acre or more of soil in Texas, you need coverage under the TCEQ Construction General Permit, TXR150000, and a Stormwater Pollution Prevention Plan in place before construction begins. Sites of five acres or more must also file a Notice of Intent. Smaller sites